A Tennessee firm bid $7.6 million to build Oxford's 24 pickleball courts at the Stone Center, under the $9 million estimate. Aldermen vote Tuesday, Nov. 17.
Oxford’s planned 24-court pickleball complex drew a low bid of $7,632,240. That is $1.4 million below the low end of the architect’s estimate. The Board of Aldermen will consider the bids at 5 p.m. Tuesday, Nov. 17, in the City Hall Courtroom.
Wagner General Contractors Inc. of Bartlett, Tennessee, submitted the low bid. It covers 18 covered courts, six outdoor courts, two parking lots and a raised platform. City staff recommend accepting it.
The figures are in a memo from Special Projects Director Mark Levy and Chief Operating Officer Hollis Green. The memo, the certified bid tabulation and the architect’s recommendation are in the Nov. 17 agenda packet on the city’s meeting portal.
What the $7.6 million buys
The bid is split into a base price and four add-on pieces, called alternates. Wagner’s prices:
| Bid item | Amount | Extra building time |
|---|---|---|
| Base bid: 18 covered courts | $6,615,159 | 360 days |
| Alternate 1: six outdoor courts | $379,045 | 30 days |
| Alternate 2: west parking lot on Molly Barr Road | $333,043 | none |
| Alternate 3: north parking lot at the Stone Center | $59,534 | none |
| Alternate 4: raised platform | $245,459 | 30 days |
| Total | $7,632,240 | 420 days |
Wagner was the low bidder under every combination of alternates, the architect said. So taking all four does not change who wins.
Twelve bids, all under $10 million
The city received 12 bids. They were opened at City Hall on Thursday, Nov. 5.
The architect, Beard + Riser Architects of Oxford, had estimated the job at $9 million to $10 million before bidding. Every full-project bid came in under $10 million, and 10 of the 12 were under $9 million. The firm said that points to a competitive bid market, not one unusual bid.
Each bidder’s full price, with the base bid and all four alternates:
| Bidder | Full project bid |
|---|---|
| Wagner General Contractors Inc. | $7,632,240 |
| Moss Carpenter Construction Co. Inc. | $8,167,500 |
| D C Services LLC | $8,193,000 |
| Zellner Construction Services LLC | $8,258,400 |
| Barnes & Brower Inc. | $8,390,981 |
| Roberts Builders Inc. | $8,475,000 |
| Linkous Construction Co. Inc. | $8,521,786 |
| AS Fornea Construction | $8,667,000 |
| Hooker Construction Inc. | $8,764,000 |
| rka Construction LLC | $8,866,990 |
| Grinder Taber & Grinder Inc. | $9,236,650 |
| ECON Construction | $9,520,574 |
Wagner’s bid is $535,260 below the next lowest, from Moss Carpenter. It is $1,367,760 below the $9 million low end of the estimate, or 15.2%.
The architect suggested the city carry a 5% contingency of $381,612 for surprises during construction. That would bring the total commitment to $8,013,852, still under the estimate.
How it will be paid for
The memo said the project will be paid for from several sources. They include money left over from the city’s 2023 and 2025 bond issues. The memo did not list the other sources or how much each would cover.
Why the city wants dedicated courts
The memo said the Oxford Park Commission saw more residents taking up pickleball in late 2023 and early 2024, and kept scheduling more gym time for play. The city now has:
- six indoor courts at the Ulysses “Coach” Howell Activity Center
- six indoor courts at the old activity center
- 12 outdoor courts at Avent Park
All three see steady use, the memo said. The Howell Center was built mainly for basketball and volleyball. When those programs use the gym, all six of its pickleball courts are unavailable.
The city first looked at the old Hayakawa building at 10 Industrial Park Drive. Its roof was too low for competitive play, columns got in the way of the courts, and it needed major repairs. The city then chose the former softball field at the Stone Center. The memo said the site is level, saw little use, can share parking and sits close to the University of Mississippi.
Design began in 2025. The plans aim to serve everyday players and to host tournaments that draw players from across the country, the memo said.
The project was first bid in 2025. Public feedback then led to changes in the court layout for tournament play. The architect said the changes were too big for a bid addendum, so the board agreed to advertise the job again with revised plans.
The Planning Commission approved the site plan Oct. 12, with variances for tall retaining walls on the sloping site. That meeting, and the plan’s courts, parking and playground, are covered in our earlier report.
When the courts could open
If the board accepts the bid, the contract would be signed once Wagner gets its performance and payment bonds. The architect’s letter works from a notice to proceed on Tuesday, Nov. 24. On that date, the 420-day contract would reach substantial completion on Tuesday, Jan. 18, 2028.
“We will explore ways to expedite the schedule with Wagner,” the architect wrote.
Also on Tuesday’s agenda
- Howell Loop lift station. City Engineer John Crawley asks the board to accept a low bid of $234,000 from MC Construction for sewer lift station improvements. The project’s line-item budget is $525,000.
- Sunday work at The Finn. Live Oak Contracting, the general contractor for The Finn development, asks to work on Sundays from Nov. 22 to the end of the year. The memo said the crew wants to finish roads and paving before a potentially wet winter.
- Paving closures in December. Century Construction, building The Magnolia Connection, asks to close parts of two streets for paving on Tuesday, Dec. 8, and Wednesday, Dec. 9. Work would start on Tyler Avenue from South Lamar to South 14th Street, then move to South 14th Street from Tyler Avenue to University Avenue. The contractor said it will try to keep one lane of one-way traffic moving on South 14th.
- Pictures with Santa. The Oxford Square Alliance seeks a permit to host Pictures with Santa and Mrs. Claus from 10 a.m. to 5 p.m. Saturday, Nov. 28.
- 208 South Lamar. Alger Design Services asks for partial sidewalk and street closures tied to a project at 208 South Lamar.
What it means for you
- Pickleball players: if the board accepts the bid Tuesday, building could start before the end of November. On the architect’s schedule, the courts would be finished in January 2028. Until then, the Howell Center, the old activity center and Avent Park remain the places to play.
- Taxpayers: the low bid leaves room under the estimate even after a 5% contingency. The city has not said how much bond money the project will use.
- Watch or attend: the board meets at 5 p.m. Tuesday at City Hall, 107 Courthouse Square. For help to attend, the agenda lists the city’s ADA coordinator at 662-232-2350.
- Drivers near South 14th Street: the December paving closures still need the board’s approval. Current closures are on our road construction page.
Source: City of Oxford Board of Aldermen agenda and agenda packet for Nov. 17, 2026, published on the city’s CivicClerk portal.
Have your say