The Oxford School District expects to spend about $13 million on Bramlett Elementary by 2028. An eight-classroom addition is being built, and phase two goes out to bid this winter.

The Oxford School District expects to have spent about $13 million on Bramlett Elementary School by the end of the 2027-28 school year. It is the largest investment the campus has seen, the district said.

The district set out the plan in an announcement Monday. Bramlett is the oldest building in the district. Some of the work is finished, an eight-classroom addition is under construction, and a second phase is due to go out for bids this winter.

What is done or under way

The most visible change so far is the cafeteria, renovated in the past few months. The district listed:

  • new furniture, flooring and paint
  • an upgraded audiovisual system
  • a refinished stage with a new stage curtain

Other projects completed or in progress, according to the district:

  • enhanced campus security
  • front office renovations
  • an eight-classroom addition, now under construction
  • a modernized cafeteria kitchen
  • improvements to special education classrooms
  • renovated classroom restrooms

That work follows an earlier classroom wing and a tornado shelter at the school, both paid for through the district’s 2023 bond referendum.

Phase 2: summer 2027

The second phase is scheduled to go out for bids in the winter of 2026-27. Construction is projected to start in summer 2027, the district said. It covers the school’s main building:

  • a new fire sprinkler system
  • new ceilings and classroom flooring
  • new millwork and paint
  • plumbing upgrades throughout the building
  • renovated classrooms and corridors

Outside, the main playground is to be renovated and expanded with new surfacing, new equipment and more fencing. The courtyard play area is to get new turf or playground surfacing and more equipment.

Much of the work will be done while school is in session.

“The plan to renovate Bramlett takes massive coordination because much of this work will be completed while school is in session,” said Steve Hurdle, the district’s chief of operations. “Months of planning have allowed us to develop a scope of work that will modernize this campus and simultaneously allow us to complete the work while educating students.”

What the $13 million covers

The district said the figure is the total for four pieces of work:

  • the classroom wing built with 2023 bond money
  • the tornado shelter, also from the bond
  • the eight-classroom addition, paid for by the district
  • the renovations in both phases

The announcement did not break the total down by project. It did not say how phase two will be paid for, and it did not mention a new bond or a tax change.

“Bramlett is one of the first campuses that our families encounter, and we believe that the facilities should mirror the excellence that our school staff exhibits daily in educating some of our youngest learners,” Interim Superintendent Germain McConnell said.

Board of Trustees President Carter Myers said the board is proud of the work. “Bramlett holds a special place in Oxford’s history and in the lives of so many of our families,” Myers said.

A school with a history

The district said the age of the building has made major upgrades hard to do without disrupting classes. Other campuses have had large renovations over the years.

After schools were integrated in 1970, Della Reed Davidson became Bramlett’s first African American principal, the district said. Della Davidson Elementary is named for her.

A black-and-white architect's drawing of a low, flat-roofed school building with long rows of windows, a covered entrance, a flagpole and cars parked along a curving drive.
The original 1968 architect's rendering of Bramlett Elementary School. Image: supplied by the Oxford School District

What it means for you

  • Bramlett families: expect construction on campus through the 2027-28 school year. The district plans much of the phase two work while classes are in session. Ask the school how drop-off, recess and events will be affected once a schedule is set.
  • Contractors: phase two is due to be advertised this winter. Watch the district’s requests for proposals page.
  • Taxpayers: the announcement proposes no new bond or millage. Our property taxes page explains how school millage appears on an Oxford tax bill.

Bramlett is one of the three projects the district named when it announced its long-term capital improvement plan Oct. 29. For grades and enrollment at every school, see our Bramlett Elementary page and the Oxford public schools guide.